25 Oct 2025
@vcunat:matrix.orgVladimír Čunát

Rebuild: linux 2264, darwin 982

07:06:08
@ivy:faggot.shivywhen is the next staging to next08:16:05
@vcunat:matrix.orgVladimír Čunát In about a week I'd expect to start a new staging-next. 08:16:58
@aloisw:julia0815.dealoisw
In reply to @k900:0upti.me
It's fixed in openssh master already
10.2 has the fix already, and can be grafted.
13:56:36
@emilazy:matrix.orgemilythere's not a strict schedule, we generally rotate between stable and unstable (and oldstable for the painful couple of months where we support that) with maybe a day or two between them to let Hydra catch up on the release channels14:01:53
@emilazy:matrix.orgemilyand it takes something like 10 days to build the average unstable cycle but it's usually lengthened by fixing important regressions etc.14:02:16
@emilazy:matrix.orgemily a rough metric is that something merged into staging should generally reach master within 2–4 weeks depending on the timing and how cycles go 14:03:15